Hornsea Projects One, Two and Three

Against a highly complex consenting landscape, RPS led the Environmental Impact Assessment (EIA) to support the delivery of three of Ørsted’s flagship offshore wind projects in the North Sea - Hornsea Project One, Hornsea Project Two and Hornsea Project Three.

 

In the UK, consent to build major infrastructure projects such as large offshore wind farms is ultimately granted by the Secretary of State. The EIA process is highly regulated and is critical to securing consent. Support provided by RPS included project management, consenting and technical services throughout the pre-application and examination phases of all three of the Hornsea projects.

Each Hornsea project has set new records for proposed offshore wind farms, and Hornsea Project Three will be the largest proposed to date, anywhere in the world. It has the potential to generate up to 2.4 GW of electricity and will cover an area offshore of approximately 700 sq. km. 

Timeline

  • 2014

    Consent for Project One was granted in December.

  • 2016

    Project Two offshore wind farm was consented in August.

  • 2018

    Project Three Development Consent submitted in May 2018.

  • 2020

    Project One commenced operation.

    Project Three Development Consent granted, December 31.

  • 2022

    Project Two is scheduled to commence operation.

1 /05
2014

Consent for Project One was granted in December.

2016

Project Two offshore wind farm was consented in August.

2018

Project Three Development Consent submitted in May 2018.

2020

Project One commenced operation.

Project Three Development Consent granted, December 31.

2022

Project Two is scheduled to commence operation.

Key details

Project name
Hornsea Projects One, Two and Three

Client
Ørsted

Location
North Sea

Services provided

  • Lead EIA consultants
  • EIA coordination and project management
  • Provision of majority of onshore technical specialists (in-house)
  • Provision of majority of offshore technical specialists (in-house)
  • Stakeholder engagement / consultation  
  • Pre-application and examination phase support
  • Expert witness advice during hearings

Challenge

Obtaining permission from the UK Government to build huge, utility-scale, offshore wind farms is challenging. A cornerstone of the process is the successful acceptance of the EIA by the Planning Inspectorate. Consent to build is dependent on accurately assessing the cumulative, and in combination, environmental impact of an increasing number of multiple wind farms and existing, and often competing, sea uses (for example oil & gas, fisheries, commercial navigation).

Furthermore, significant areas of the sea bed and coastal regions have been designated as protected areas which limits infrastructure development. Adding to the complexity are the statutory regulators and consultees which are becoming increasingly active in their defence of these protected marine areas.

Offshore wind projects can also include complex onshore elements such as an onshore substation and lengthy cable runs to the grid connection. Both require nuanced engagement with multiple landowners and stakeholders.

RPS was engaged by Orsted to deliver the EIA for three separate flagship Orsted projects.

Hornsea projects 1, 2, 3 - project image (shutterstock_152682614).jpg

Solution

RPS has deep expertise in the delivery of offshore renewables. Our team of project managers, EIA experts and technical leads bring a comprehensive understanding of a range of potential marine and terrestrial, human, biological and physical environmental impacts to meet the challenges of each of the Hornsea projects.

We provided key support for public and stakeholder consultation, completion of the Preliminary Environmental Information Report (PEIR), drafting the environmental assessment, and submission of a final environmental statement.

The project potentially impacted ecologically sensitive areas so RPS lead on a wide range of technical issues including assessment of visual impact concerns (key to onshore substation consent), environmental planning for cable-routing and extensive ornithological studies to monitor potential impacts for seabirds.

During the Examination phase, RPS supported Orsted providing responses to the Examining Authority’s questions, authoring additional documents, and input into the Development Consent Order and Marine Licence conditions. We also provided expert witnesses during the hearings.

As lead EIA consultant, RPS project managers:

  • Coordinated the EIA
  • Managed the team of technical specialists
  • Liaised with engineering teams
  • Supported the Development Consent Orders and deemed Marine Licences.

Project statistics

1.2 GW
Hornsea Project One capacity - enough power for 1 million homes.
1.8GW
Hornsea Project Two capacity - enough power for 1.6 million homes.
2.4GW
Proposed Project Three capacity - enough to power over 2 million homes.
4.6 million
Homes can be powered by Hornsea once all three projects have commenced operation.

Contact us

Williams_Alun_20181212.png

Alun Williams

Global Offshore Renewables Director T: +44 (0) 1483 746 500 Email
View profile »
Woking | UK
Linnane_Kevin_20181210_waistup_highres.jpg

Kevin Linnane

Associate Director, Marine Ecology T: +44 (0) 1483 746500 Email
View profile »
Chepstow | UK

Get in touch

Your contact information:

All fields are mandatory *

Get in touch

Your contact information:

All fields are mandatory *