Livingston Regional Water Supply System Expansion

RPS completed preliminary engineering, final design, bid-phase and construction-phase services for expansion of the Trinity River Authority Livingston Water Supply System on Lake Livingston. The project included a raw water intake in Lake Livingston, a raw water pump station and approximately 5,000 linear feet of raw water transmission line. The 5 MGD plant expansion included a new raw water metering and flash mix structure, a new SUPERPULSATOR clarifier, conversion of two existing solids contact clarifiers to SUPERPULSATOR clarifiers, complete replacement of all chemical feed systems, new dual media filters with air scour backwash, new backwash pumping facilities, replacement of the 480-volt distribution system in the plant and addition of standby generators. 

Timeline

  • 2016

    Completion Date

1 /01
2016

Completion Date

Key Details

Project Name

Livingston Regional Water Supply

Client

Trinity River Authority (TRA)

Sector

  • Water management

Location

  • Livingston, Texas, USA

Services Provided

  • Civil engineering
  • Water and wastewater infrastructure design

 

Challenge

A nearby prison created some concerns about security. 

Solution

RPS incorporated security measures into the design to protect the plant infrastructure and its employees.