Renescience Northwich

Renescience is the first facility of its kind in the UK to use new technologies recovering resources from waste and generating renewable electricity through treatment with enzymes, mechanical sorting and anaerobic digestion.

We provided consultancy services from concept design, planning, detailed design through to construction on this traditionally procured scheme; presenting the project to the planning committee that successfully approved the scheme at the first time of asking.

The plant comprises a waste bunker with overhead crane, reception hall, pre-sorting areas, bioreactor hall, sorting and loading halls as well as associated offices and control room.

External facilities include an anaerobic digestion tank farm, CHP engines, main stack, gas flare, ancillary storage sheds, a water treatment plant plus weighbridges and parking.

Key details

Project name
Renescience Energy from Waste


Client
DONG Energy (now Ørsted)


Location
Northwich, England

Services provided

  • Architecture
  • Structural engineering
  • Civil engineering
  • Building services
  • Fire engineering
  • Planning
  • Public consultation
  • EIA
  • CDM / principal designer

Challenge

Challenges included:

  • Tight timescale - the programme was driven by the need to achieve first operation by April 2017 in order to gain Renewables Obligation support
  • A heavily constrained site
  • Challenging programme and budget
  • Client’s insurers requirements
  • Assisting with the development, coordination and delivery of an innovative and complex process solution
REnescience Efw - Project image 2.jpg

Solution

We prepared the environmental permit application alongside the planning application, EIA, ground investigation, and animal by-products application. The documents were fully prepared in-house drawing on efficiencies with the EIA assessments and included permit specific assessments and plans including a Fire Prevention Plan, Application Site Condition Report, detailed Odour Management Plan and H1 Assessment. As the first plant of its type to be permitted under the Environmental Permitting Regulations (EPR), careful consideration was given to presentation of the BAT Assessment for the DONG Energy enzymatic technology.

We were additionally appointed to provide the architectural and engineering design of the facility. To meet the extremely challenging programme and budget, we developed a close working relationship with the client and technology designer to provide an innovative solution.

Building Information Modelling (BIM) and software including Autodesk Revit and Navisworks were used as an essential part of the design process. This helped co-ordinate the facility with the complex MHP and process equipment through the use of clash avoidance and further assisted in developing a collaborative working environment.

The EA issued the environmental permit in September 2017, leaving a matter of months to discharge pre-operational conditions and allow the facility to be brought into operation. Due to the tight timescale we worked closely with the EA to secure advance notice of likely conditions to ensure rapid discharge of conditions could be achieved.

We subsequently supported DONG Energy in the preparation of the commissioning phase plan, accident management plan, and energy efficiency plan and provided support to regularise minor technical changes to the design prior to its operation. In conjunction with our in-house design and engineering team RPS also discharged the pre-operational condition confirming all containment structures at the site had been designed and constructed fully in accordance with BAT and CIRIA guidance.

With our support DONG Energy discharged all pre-operational conditions in time to achieve its operational deadline.

Project statistics

120,000tpa
waste treatment capacity
110,000
homes equivalent waste treatment capacity
9,500
homes can be powered by energy generated
5MW
baseload electricity generation
95%
potential recyclable material recovery rate
First
commercial scale waste to bioenergy plant using new enymatic treatment technology
First
plant of its type permitted under UK Environmental Permitting Regulations

Get in touch

Your contact information:

All fields are mandatory *

Message: