We are delivering ground investigation services across the full length of the new High Speed 2 (HS2) rail link between London Euston and Birmingham Curzon St, the UK’s largest ever ground investigation project.
Throughout the initial preliminary design, value engineering and detailed geotechnical design phases, we have delivered geotechnical data for HS2. The most successful company on the Framework, we are operating on packages across the route, including at key locations required for managing geotechnical risk of major structures such as tunnels, deep cuttings and underground stations.
Project name
High Speed 2 Ground Investigation Works
Client
HS2 Ltd, Fusion, Balfour Beatty, Vinci, Effiage, Kier
Location
London to Birmingham proposed route of HS2 Phase 1 (Euston Station - Camden, Oxfordshire, Northamptonshire, Warwickshire, West Midlands)
Â
Services provided
As a project of immense scale, managing the geotechnical risk demands a large range of specialist techniques to produce the vast amount of data.
On site, we have employed multiple techniques including:
Our team of ground investigation consultants have delivered these complex techniques and testing with their specialist knowledge, expertise and supervision.
Â
From the outset, we developed a robust data management plan and quality management system to ensure accurate, efficient and consistent data processing, enabling geotechnical risks to be managed at each stage of the project design.
Successful delivery of the data management plan was achieved by providing AGS4 and Ground Investigation data management training to all project and site staff. Â We also arranged training, guidance and workshops to some specialist contractors and laboratories that were not prepared for reporting AGS4 data.
We continue to improve data management and have developed an innovative cloud-based data capture system that will enable all data from the field to be instantaneously logged and recorded remotely through the use of a tablet-based GIS tool. This new and improved system is being rolled out in the HS2 detailed design phase and will allow live tracking of data capture, resulting in further improvements in data quality assurance and management.
Â
Your contact information:
All fields are mandatory *
RPS is committed to protecting and respecting your privacy. We will only use your personal information to administer your account and to provide the products and services you have requested. We would also like to contact you about our products and services, as well as other content that may be of interest to you.
Your contact information:
All fields are mandatory *
RPS is committed to protecting and respecting your privacy. We will only use your personal information to administer your account and to provide the products and services you have requested. We would also like to contact you about our products and services, as well as other content that may be of interest to you.