When a five-year-old business case meets today's construction market
Transport infrastructure projects can spend years progressing through business cases, planning, approvals and funding decisions before construction begins. During that time, the construction market can change considerably.
Tom Gibbs
An estimate is only as strong as the information behind it
Labour availability, material costs, supply chain conditions and project requirements may look very different from when the original investment decision was made. Yet when funding is secured and a project moves towards delivery, there can be an expectation that work will proceed against the budget, scope and schedule established years earlier.
This presents an important challenge for infrastructure owners and delivery teams: how do you ensure a project approved under yesterday's assumptions remains achievable in today's construction market?
What changes between business case and construction?
A business case provides the foundation for an investment decision. It establishes the need for a project, considers available options and assesses anticipated costs, benefits and delivery requirements. However, the information available during early planning is rarely as detailed as it will be when a project reaches procurement or construction. Over several years, cost estimates may need to be revised, design requirements can evolve and the practical realities of delivery become clearer.
Market conditions add another layer of uncertainty. Infrastructure Australia's 2025 Infrastructure Market Capacity Report identified labour and material costs among the leading causes of project delivery disruption. Its industry survey found that 64% of respondents identified material costs as a major or significant disruption, followed by labour costs (63%) and labour and skills shortages (59%).
These pressures do not affect every project equally. Their impact depends on location, timing, scope, procurement arrangements and the capacity of the market to deliver the required work.
New Zealand's National Infrastructure Pipeline also demonstrates how project estimates evolve. Its June 2026 update recorded both increases and decreases in expected project costs across infrastructure initiatives at different stages of planning and construction.
The report notes that estimates prepared during early planning generally carry a lower degree of confidence and are more readily revised as planning progresses. Changes in reported values do not necessarily represent construction cost escalation; they can also reflect a more developed understanding of project requirements.
The lesson is not that early estimates are necessarily wrong. It is that they reflect the information, market conditions and assumptions available at a particular point in time. For infrastructure owners, the important question is whether those assumptions remain appropriate when the project is ready to move forward.
The risk of carrying outdated assumptions into delivery
When a project progresses towards construction without reassessing its original assumptions, the difference between the approved budget and current delivery requirements can become difficult to manage. A cost estimate developed several years earlier may no longer reflect prevailing market rates or the full scope of work now understood to be necessary.
Similarly, procurement strategies and construction programs developed during early planning may need to be reconsidered against current contractor availability, resource requirements and delivery constraints. This is particularly relevant to major transport infrastructure, where construction must often be coordinated around operational networks, restricted access periods, existing assets and multiple delivery interfaces.
The challenge extends beyond cost escalation. An outdated estimate may reflect a combination of changes in market pricing, greater design maturity, revised scope requirements and delivery risks that were not fully understood when the original business case was prepared.
Understanding these differences matters because they may require different responses. A change in market pricing may call for updated estimates or procurement advice. A change in scope may require a review of project requirements, while new delivery constraints could affect sequencing, scheduling or risk allowances.
A project can remain strategically important while requiring adjustments to how it is funded, procured or delivered. Identifying these requirements before construction commitments are made gives decision-makers a greater opportunity to consider their options and respond appropriately.
Re-establishing a realistic project baseline
One of the most valuable steps between investment approval and construction is reassessing the project's baseline. A project baseline establishes the agreed scope, budget and schedule against which delivery performance can be measured. For infrastructure projects that have spent several years progressing through planning and approvals, revisiting these foundations helps determine whether the original assumptions still provide a realistic basis for delivery.
The starting point is understanding what has changed. This means reviewing the current project scope, assessing the maturity of the design and confirming whether the requirements being taken to market align with those considered in the original business case.
Cost estimates should then be tested against contemporary market conditions, including labour and material pricing, contractor availability, procurement requirements and the risks associated with delivery. However, establishing a realistic baseline requires more than simply applying an escalation allowance to an earlier construction estimate. It requires an integrated understanding of how scope, cost, procurement, risk and scheduling decisions influence one another.
Cost advisory specialists can assess the basis of existing estimates, consider appropriate contingency and escalation allowances, and help determine whether the budget remains aligned with the proposed scope and market conditions. Project management and delivery specialists bring a complementary perspective, examining construction sequencing, procurement options, delivery constraints and the practical requirements of implementing the work. Bringing these disciplines together helps project teams identify where assumptions may no longer align and what decisions are needed to establish a more achievable delivery strategy.
For major infrastructure programs, this assessment may also need to extend beyond individual projects. Where multiple initiatives are progressing through procurement and construction, competition for specialist labour, contractors and materials can influence market capacity and delivery timing. A realistic program therefore needs to consider not only whether individual projects are affordable, but whether their proposed delivery schedules and resource requirements are achievable within the broader infrastructure pipeline.
This aligns with the principles of the New Zealand Treasury's Better Business Cases framework, which considers whether an investment is commercially viable, financially affordable and achievable. These considerations are closely connected, but they are not interchangeable.
The objective is not to eliminate uncertainty. It is to understand it, assess its potential impact and provide decision-makers with a reliable basis for progressing.
Better decisions before delivery begins
For infrastructure owners, the transition from business case to construction presents an important opportunity to test whether the project remains ready for delivery. This does not necessarily mean repeating the entire business case process. Instead, it means taking a proportionate approach to reviewing the assumptions most likely to affect project outcomes, with the level of assessment reflecting the complexity, maturity and risks of the investment.
Early engagement with cost advisors, project managers, procurement specialists and delivery teams can help identify gaps between the original investment proposal and current construction requirements. It can also provide greater clarity around the decisions that need to be made, whether that involves refining scope, updating estimates, reviewing procurement options, strengthening project controls or reconsidering delivery sequencing. For organisations managing major infrastructure programs, maintaining realistic and consistent project information also supports better investment prioritisation and portfolio-level decision-making.
RPS brings together Cost Advisory, Project Management and project controls expertise to help infrastructure owners navigate these challenges. From reassessing cost assumptions and delivery risks to strengthening procurement planning, forecasting and project governance, our teams help clients establish a clearer, more achievable path from investment approval to construction.
An approved business case should provide a foundation for delivery, not become a set of assumptions that remain unchanged regardless of circumstances.
For infrastructure owners preparing to deliver complex projects, the strongest starting point is not simply an approved budget. It is a realistic understanding of what needs to be delivered, what it is likely to cost and how it can be achieved in today's construction market.